Solar & Battery Grid Connections: ENA EREC G98, G99 & G100 Explained

Deploying distributed energy resources (solar photovoltaic arrays, battery energy storage systems, and micro-generators) in parallel with the UK public electricity network requires navigation of strict DNO governance. Installers must understand the critical legal boundary between ENA Engineering Recommendation G98 ("Fit and Inform") and EREC G99 (Prior Application Required), alongside the rigid 5-second fail-safe closed-loop requirements of EREC G100 Issue 2 Export Limitation Schemes. This manual provides the definitive statutory framework and technical criteria for UK grid connections.

CLASSIFICATIONStatutory compliance guide
STATUTORY AUTHORITYESQCR 2002 REG 22 // DISTRIBUTION CODE // EAWR 1989
PRIMARY STANDARDSENA EREC G98 // EREC G99 // EREC G100 ISSUE 2
ENGINEERING AUDIT30 October 2026 : ADRIAN KING
STATUTORY GRID BOUNDARY & LEGAL DIRECTIVE

This document is an authoritative engineering manual compiled for renewable energy consultants, electrical contractors, and commercial dutyholders. It defines the mandatory legal pathways and engineering submissions required under the Electricity Safety, Quality and Continuity Regulations 2002 (ESQCR) and the UK Distribution Code. Connecting generating or storage equipment in parallel with the public network without formal DNO notification or prior consent constitutes a criminal offense under Regulation 22 of the ESQCR 2002, punishable by statutory disconnection, substantial network reinstatement fines, and criminal prosecution.

STATUTORY REGULATIONESQCR 2002 REGULATION 22 // DISTRIBUTION CODE LICENSE CONDITIONS
GOVERNING RECOMMENDATIONS:ENA EREC G98 AMD 7 // EREC G99 AMD 10 // EREC G100 ISSUE 2Jump to Statutory Duty Matrix ↓
SCREEN 1 AUDITENA GOVERNANCE

10-Second Engineering Summary: DNO Connection Parameters

G98 MICRO-GENERATOR CAP (1-PHASE)3.68 kW (16 A)Fit & Inform: notify DNO within 28 days of commissioning
G98 MICRO-GENERATOR CAP (3-PHASE)11.04 kW (16 A/PHASE)Total aggregate capacity across all generation & storage
G99 FAST-TRACK SLA10 WORKING DAYSForm A2-1 / A2-2 expedited prior consent from DNO
EREC G100 FAIL-SAFE WINDOW≤ 5.0 SECONDSComms loss or CT failure triggers immediate curtailment
SECTION 01

The Statutory Framework: ESQCR 2002 Regulation 22 & Distribution Code

In the United Kingdom, operating generating equipment in parallel with the public low-voltage distribution network is governed by primary statutory legislation. Compliance with British Standards (BS 7671) alone is insufficient; explicit network connection legalities must be satisfied.

Under Regulation 22 of the Electricity Safety, Quality and Continuity Regulations 2002 (SI 2002/2665):

"No person shall connect a source of electrical energy in parallel with an electrical network of a distributor without the distributor's formal notification or agreement..."
CRIMINAL LIABILITY & UNLAWFUL ENERGISATION HAZARDS

Energising a commercial solar array or battery inverter without receiving DNO formal agreement (for installations exceeding 16A per phase) constitutes an unlawful connection. The DNO has the statutory authority to physically sever the consumer service intake. Furthermore, unauthorised generation can cause severe local voltage rise (exceeding the statutory +10% limit of 253V), trip local distribution transformer tap changers, and endanger DNO engineering crews executing line maintenance.

The Energy Networks Association (ENA), representing all six UK Distribution Network Operators (UK Power Networks, National Grid Electricity Distribution, Scottish and Southern Electricity Networks, SP Energy Networks, Electricity North West, and Northern Powergrid), codifies compliance into three engineering recommendations: G98, G99, and G100.

SECTION 02

ENA EREC G98: The 16A Per Phase "Fit and Inform" Pathway

ENA Engineering Recommendation G98 applies exclusively to Micro-generators of up to and including 16 A per phase connected at low voltage. This framework was designed to facilitate small domestic renewable installations without imposing administrative delays:

Supply TypePhase Current CapMaximum AC Power RatingProcedural Rule
Single-Phase (230V)16.0 A3.68 kW maximum continuous AC outputCommission first, submit Form B within 28 days
Three-Phase (400V)16.0 A per phase11.04 kW maximum continuous AC output (across 3 phases)Commission first, submit Form B within 28 days
Combined Solar + BatteryTotal aggregate > 16 AExceeds 3.68 kW simultaneous AC generationG98 VOID: G99 APPLICATION REQUIRED

A vital rule under G98 is that capacity calculations evaluate aggregate active AC inverter capability, not solar panel peak DC wattage (kWp). If an installation features 5.0 kWp of solar panels connected to a certified 3.68 kW AC inverter, the installation is fully compliant with G98 single-phase limits. However, if an installer fits a 3.68 kW solar inverter alongside a 3.0 kW AC-coupled battery storage inverter on the same phase, total capacity is 6.68 kW (29 A), rendering G98 completely invalid.

SECTION 03

Connection Architecture & Master Compliance Decision Matrix

The complete decision architecture governing UK grid connections is illustrated below. It maps the precise boundaries between G98 Fit & Inform, G99 Fast-Track pathways, full network studies, and EREC G100 closed-loop export limiters:

ENA EREC G98 / G99 / G100 // UK DISTRIBUTED GENERATION CONNECTION ARCHITECTUREESQCR REG 22 // 16A/PHASE // G99 FAST-TRACK // G100PANEL 1: 16A/PHASE DIVIDING THRESHOLDFit and Inform versus Prior Application gateAGGREGATE GENERATION CAPACITY (AC OUTPUT)TOTAL AC≤ 16A / > 16A?G98 PATHFIT & INFORM≤ 28 DAYSG99 PATHPRIOR PERMISSIONNO ENERGISESTATUTORY ESQCR REGULATION 22• Unauthorised parallel connection is a statutory criminal offense• G98 Single-phase limit: 3.68 kW (16 A at 230 V)• G98 Three-phase limit: 11.04 kW (16 A per phase)G98 ELIGIBILITY BOUNDARIES• Single-Phase Cap:3.68 kW (16 A)• Three Phase Capacity Cap:11.04 kW (48 A total)• Inverter Pre-Condition:ENA Type Test Registered• Commissioning Window:Notify within 28 daysPANEL 2: G99 APPLICATION PATHWAYSFast-Track A2-1/A2-2 vs full DNO thermal reviewG99 APPROVAL TIMELINES & FORMSFAST-TRACK A2-1Storage + Gen ≤ 32A, Export ≤ 16A10 DAYSFAST-TRACK A2-2Pure Battery Storage with Zero Export10 DAYSFULL G99 STUDYCapacity > 32A or Network Constraint45-65 DAYSFAST-TRACK CONDITIONS OF ADMISSION• Inverters must be verified on ENA Type Test database• Export Limitation Scheme must be fully certified to G100• Prior written consent mandatory before commissioningDNO SLA & SUBMISSION TIMELINES• Fast-Track Form:Form A2-1 / Form A2-2• Fast-Track Statutory Response:≤ 10 Working Days• Full Assessment:45-65 Work Days• Witness Testing:Type Tested: WaivedPANEL 3: EREC G100 EXPORT LIMIT5-second fail-safe watchdog & CT directionalityEREC G100 ISSUE 2 CLOSED-LOOP CONTROLBOUNDARYCLASS 0.5 CT≤ 1.0s SAMPLINGPOWERLIMITERLOCKED CONFINVERTERTHROTTLE≤ 5.0sG100 FAIL-SAFE MANDATE• Loss of CT signal triggers immediate reduction to safe export limit• Maximum allowable curtailment time window: ≤ 5.0 seconds• System parameters must be protected by password or physical sealEREC G100 ISSUE 2 TECHNICAL SPEC• Excursion Response Time:≤ 5.0 seconds to limit• Measurement Accuracy:Class 0.5 or Class 1 CT• Comms Failure Default:Fall back to safe export• Security Lock:Seal or PasswordFIGURE 1: ENA EREC G98 / G99 / G100 GRID CONNECTION ARCHITECTURE, FAST-TRACK PATHWAYS & EXPORT LIMITATIONUK ELECTRICAL WORKSTATION // AUTHORITATIVE FIELD SPECIFICATION
Figure 1: UK Distributed Generation Connection Architecture under ENA Engineering Recommendations. Left: 16A per phase capacity threshold dividing G98 Fit & Inform from G99 Prior Application. Center: G99 Fast-Track pathways (Form A2-1, Form A2-2) versus full network study. Right: EREC G100 Issue 2 Export Limitation Scheme closed-loop control with 5-second fail-safe curtailment watchdog.

Before commencing work on any generation or storage project, the engineer must identify the mandatory submission route using the following Master Compliance Matrix:

Application PathwayCapacity & Technical CriteriaLegal MandateDNO Forms & Statutory TimelinesBreach Consequence
G98 Single PremisesSingle or 3-phase, ≤ 16A/phase. Inverter verified on ENA Type Test register.ESQCR 2002 Reg 22(2)(a)Form B: Post-commissioning notification within 28 days. Zero prior wait.Administrative penalty; voided insurance.
G98 Multiple PremisesMultiple properties on same low-voltage feeder (e.g. new housing scheme).ENA EREC G98 Cl 6.2Form C: Prior application required to model transformer cluster loading.Substation fuse rupture; developer liability.
G99 Fast-Track A2-1Storage + generation ≤ 32A/phase total, with export limited to ≤ 16A/phase.ENA EREC G99 Cl 3.3.1Form A2-1: Prior application. DNO response within 10 working days.Unauthorised parallel connection breach.
G99 Fast-Track A2-2Pure battery storage systems of any size with certified zero-export limiter.ENA EREC G99 Cl 3.3.2Form A2-2: Prior application. DNO response within 10 working days.Immediate DNO disconnection directive.
G99 Full Standard StudyCapacity > 32A/phase or export capacity exceeding local network thermal headroom.ENA EREC G99 Cl 3.4Standard Application Form (SAF): Full engineering review. 45-65 working days.Criminal offense under ESQCR Regulation 22.
EREC G100 Issue 2Any installation deploying active power curtailment to prevent network overload.Distribution Code DOC 5G100 Appendix B: Commissioning form with step-change tests logged.Forced curtailment to safe fallback floor.
SECTION 04

ENA EREC G99: Fast-Track Pathways vs Full Network Study

Whenever total generation capacity exceeds 16 A per phase, or where equipment is not registered on the ENA Type Test database, ENA Engineering Recommendation G99 applies.

Historically, all G99 applications took up to 65 working days to process. To support the rapid rollout of domestic and light commercial battery systems, the ENA introduced the Fast-Track Application Procedures:

Fast-Track CategoryTarget Installation ArchitectureOperational Power ConstraintsDNO Approval Window
Fast-Track A2-1Domestic solar PV paired with battery storage on the same single-phase supplyCombined inverter capacity ≤ 32 A (7.36 kW); export hardware limited to ≤ 16 A (3.68 kW)10 Working Days (Standard turnaround)
Fast-Track A2-2Standalone battery storage system installed to capitalise on agile time-of-use tariffsBattery capacity up to service cut-out rating; export hardware limited to strictly 0 kW (Zero Export)10 Working Days (Standard turnaround)
Fast-Track A2-3Commercial fleet EV charging infrastructure paired with vehicle-to-grid (V2G) chargersV2G discharge capacity controlled by G100 limiter to prevent exceeding import/export agreement10 Working Days (Standard turnaround)
FAST-TRACK REJECTION CRITERIA: AVOID ADMINISTRATIVE RESUBMISSION

A fast-track application will be summarily rejected and kicked into the 65-day full study queue if: (1) The inverters are not listed on the ENA Type Test Register; (2) The proposed export limit exceeds 16 A per phase without prior network agreement; or (3) The single-line diagram (SLD) fails to show the exact location and wiring of the EREC G100 current sensing CTs.

SECTION 05

EREC G100 Issue 2: Fail-Safe Closed-Loop Export Limitation Schemes

In many UK postcodes, the local low-voltage distribution network is severely constrained: local distribution transformers cannot accept additional reverse power flow without thermal overload or overvoltage tripping. In these scenarios, DNOs issue a connection offer with a restricted export allowance (e.g. 0 kW export, or 3.68 kW on an 11 kW array).

To satisfy this condition, an Export Limitation Scheme (ELS) complying with ENA EREC G100 Issue 2 must be installed. G100 Issue 2 enforces strict fail-safe closed-loop control:

G100 Technical ParameterIssue 2 Performance MandateFailure Mode MitigationCompliance Verification
Maximum Excursion Time≤ 5.0 seconds to throttle export back below agreed DNO limitPrevents local distribution transformer reverse power tripsWitnessed on-site step load drop test
Current Sensing AccuracyClass 0.5 or Class 1.0 CTs complying with BS EN 61869-2Guarantees accurate real-time current measurement at intake boundaryCalibration certificate check
Comms Loss WatchdogLoss of communication between meter and inverter causes immediate curtailmentIf data cable severed, inverter must throttle export to zero within 5.0sPhysical cable disconnection test
Anti-Tamper SecuritySettings protected by password, firmware hash, or physical tamper sealPrevents system owner from overriding export ceiling via mobile appAudit check of installer credentials
SECTION 06

Bench Notes: Field Wisdom & Deep Regulatory Derivations

Authoritative engineering derivations, common traps, and DNO submission wisdom:

Bench Note 1: The 16A Calculation & The 230V Nominal Voltage Trap

Under UK national standards (BS 7671 and the Electricity Supply Regulations), nominal single-phase voltage is codified as 230V AC. The mathematical boundary under ENA EREC G98 is strictly derived as: 16.0 A × 230 V = 3,680 Watts (3.68 kW).

A frequent error made by overseas inverter manufacturers and novice designers is calculating power using 240V (16 A × 240 V = 3.84 kW). If an inverter data sheet declares maximum continuous AC power as 3.8 kW or 4.0 kW, the DNO portal will reject a G98 submission instantly. Always confirm that the maximum continuous AC active power rating on the inverter rating plate is rated ≤ 3,680W.

Bench Note 2: ENA Type Test Register Verification Protocol

Never install or specify an inverter based solely on marketing literature claiming "UK compliant". Before placing purchase orders, the engineer must verify the exact model number and firmware version on the public ENA Type Test Register.

The ENA register confirms that the device has undergone laboratory witness testing for: (1) Under-frequency and over-frequency trip thresholds (47.0 Hz and 52.0 Hz); (2) Under-voltage and over-voltage trip stages (Stage 1: 262.2V 1.0s, Stage 2: 273.7V 0.5s); and (3) Loss of Mains (LoM) protection using Rate of Change of Frequency (RoCoF) set at 1.0 Hz/s with a 500 ms time delay. If the model number does not appear exactly on the register, the installation cannot use G98 or G99 Fast-Track pathways.

Bench Note 3: CT Clamp Orientation & Directionality Verification in Plant Rooms

Over 80% of EREC G100 commissioning test failures are caused by backward current transformer (CT) clamp installation.

Every current transformer bears an arrow indicating the direction of positive grid power flow (typically pointing from the DNO service fuse toward the consumer distribution board). If an installer clips the CT clamp on backwards: (1) Power consumption is recorded as export, and power generation is recorded as import; (2) When the solar array exports power, the limiter reads it as grid demand and ramps inverter generation up rather than down; (3) Within seconds, export exceeds network limits, triggering G100 watchdog lockout. Always verify CT directionality on the inverter commissioning display before conducting live step-load tests.

Bench Note 4: The 28-Day G98 Notification Window & Building Control Part P

While G98 permits "Fit and Inform", this does not mean notification is optional. The installer has a mandatory statutory requirement to submit the completed G98 Commissioning Form (Form B) alongside the manufacturer type test certificate to the host DNO within 28 days of commissioning.

Failure to notify within 28 days causes the DNO to log an unapproved generation flag against the MPAN (Meter Point Administration Number). This prevents the property owner from registering for the Smart Export Guarantee (SEG) with electricity suppliers, depriving them of export revenue. In addition, UK competent person schemes (NICEIC, NAPIT) require DNO notification receipts prior to issuing Building Regulations Part P compliance certificates.

SECTION 07

Statutory Duty Matrix: Primary UK Grid Legislation

Connecting distributed energy plant to private and public networks carries statutory legal duties under UK parliamentary legislation:

Governing StatuteSpecific ProvisionLegal ClassificationStatutory Duty & Compliance Verification
ESQCR 2002Regulation 22(1)ABSOLUTE DUTYNo connection in parallel without distributor formal agreement. Installations > 16A/phase must receive formal connection offer prior to energisation.
ESQCR 2002Regulation 22(2)(a)STATUTORY EXEMPTIONProvides legal exemption for micro-generators ≤ 16A/phase complying with EREC G98, provided notification is delivered within 28 days.
EAWR 1989Regulation 4(1)ABSOLUTE DUTYAll systems shall be constructed and operated to prevent danger. Network protection relays (RoCoF, overvoltage) prevent out-of-phase islanding hazards.
EAWR 1989Regulation 16ABSOLUTE DUTYPersons must possess technical knowledge to prevent danger. Testing and commissioning must be executed by qualified, certified engineers.
Distribution CodeDPC 7 & DOC 5LICENSE CONDITIONDistribution Planning and Operating Codes mandate active export curtailment under G100 to protect grid stability and prevent substation damage.