3-Phase Induction Motor: TEFC, 6-Stud Terminal Box & Kloss Workbench

Explore how a 3-phase supply creates a Rotating Magnetic Field (RMF) inside a cast-iron TEFC induction motor. Configure Star or Delta links on the BS EN 60034-8 6-stud terminal box, inspect Kloss torque-speed curves, and diagnose workshop faults.

Motors & Drives10 Min Interactive
• BS EN 60034-1:2022
C&G 2365 Unit 202

3-Phase Squirrel Cage Induction Motor Diagnostic Workbench

400V 50Hz 3-Phase Supply → BS EN 60034-8 6-Stud Terminal Board → 7.5 kW Cast-Iron TEFC Stator
• READY (STOPPED)INTERACTIVE 3D LAB
View Preset:
Camera Angle:
Visibility:
Left-Drag: Orbit • Right-Drag: Pan • Scroll: Zoom • Tap Part: Inspect
1. 400V DOL INCOMER & CONTACTOR BS EN 60947-4-1 • Category AC-3 ISOLATOR Q1 CONTACTOR KM1 OPEN OVERLOAD F1 14.3 A 01 L1 02 L2 03 L3 PE (BS 7671 Reg 543) 2A. IEC 60617 STATOR COILS (DELTA 400V) Rated Winding Voltage: 400V RMS • IE3 Premium U1 U2 PHASE U (400V) V1 V2 PHASE V (400V) W1 W2 PHASE W (400V) DELTA MESH (Δ) V_ph = 400.0 V Rated 7.5 kW Torque 2B. BS EN 60034-8 6-STUD TERMINAL BOARD W2 U2 V2 U1 (L1) V1 (L2) W1 (L3) PE HTR 3.0 Nm Torque 3. 120° PHASOR RETICLE & RMF VECTOR Sequence: L1-L2-L3 (CW) L1 L2 L3 LINE VOLTAGE (V_L-L): 400.0 V RMS WINDING VOLTAGE (V_ph): 400 V RMS LINE CURRENT (I_L): 0.0 A SYNCHRONOUS SPEED (N_s): 1500 RPM (4-Pole) AVAILABLE TORQUE: 100% (Rated 7.5kW) 4. STATOR CONDUCTOR & TERMINAL SCHEDULE (BS 7671 TABLE 51 / BS EN 60034-8) STUD WIRE HARMONISED COLOUR ELECTRICAL FUNCTION TORQUE / REF U1 / W2 01 Brown / Red Collar Phase 1 Winding (0 deg Ref) 3.0 Nm • M5 Stud V1 / U2 02 Black / Yellow Collar Phase 2 Winding (-120 deg) 3.0 Nm • M5 Stud W1 / V2 03 Grey / Blue Collar Phase 3 Winding (-240 deg) 3.0 Nm • M5 Stud PE / HTR PE / 09 Green/Yellow & Orange Chassis Earth & Space Heater 4.5 Nm • M6 Stud ISO 7200 WORKING DRAWING • DWG: UK-EE-IND-MTR-01 3-PHASE CAGE STATOR SCHEMATIC CONNECTION: DELTA 400V (RATED) RATING: 7.5 kW 400V 50Hz STANDARDS: BS EN 60034-8 / BS 7671 FRAME & DUTY: 132M • S1 Continuous
LAYER 3: WORKBENCH CONTROL DECK

Motor Control Station & Commissioning Bench

BS EN 60204-1 §9.2.3.3 Stop Priority
01COMMISSIONING PARAMETERSBS EN 60034-1
02OPERATOR CONTROL STATION22mm IP65 Actuators
Supply healthy. Motor stopped and ready.
SUPPLY
RUN
O/L TRIP
CAT 0 STOP
ISO 13850
START (I)
STOP (O)
RESET TRIP
EMERGENCY STOP
SPEED0 RPM
SLIP0.0 %
LINE I0.0 A
PF0.85
SHAFT0.0 kW
LAYER 4: TIME-DOMAIN OSCILLOSCOPE

3-Phase Stator Currents & RMF Vector

IEC 60034-1 Sinusoids
Phase U (Brown L1) Phase V (Black L2) Phase W (Grey L3)Timebase: 5 ms / Div
LINE CURRENT0.0 A
FREQUENCY50.0 Hz
INRUSH RATIO0.0 x FLC
RMF FLUX MAG0.00 Bmax
LAYER 4: KLOSS CHARACTERISTIC

Analytical Torque-Speed Curve

Dynamic Operating Point
Delta 400V (Rated) Star 400V (Derated 33%) Operating Point
SHAFT SPEED0 RPM
OPERATING SLIP0.00 %
SHAFT TORQUE0.0 Nm
POWER FACTOR0.85
LAYER 5: GLASS-BOX CALCULATION PAD

First-Principles Electromagnetic Derivations

Every parameter on this workbench traces directly to statutory formulas. Derived below step-by-step for the 7.5 kW 4-pole motor.

RefFormula DescriptionGoverning StandardFormulaLive SubstitutionCalculated Result
STEP 1Synchronous Magnetic SpeedBS EN 60034-1 §6N_s = (120 × f) / p(120 × 50.0) / 41500.0 RPM
STEP 2Per-Unit Operational SlipBS EN 60034-1 §7s = (N_s - N_r) / N_s(1500.0 - 1450.0) / 1500.00.0333 (3.33%)
STEP 3Rotor Induced Slip FrequencyElectromagneticsf_r = s × f0.0333 × 50.01.67 Hz
STEP 4Rated Full Load Current (FLC)BS 7671 Table 41.3I_FLC = P / (√3 × V × cosφ × η)7500 / (√3 × 400 × 0.85 × 0.895)14.3 A (Delta) / 8.25 A (Star)
STEP 5Shaft Mechanical TorqueBS EN 60034-1 §8T = P / ω_m = P / (2π N_r / 60)7500 / (2π × 1450 / 60)49.4 Nm (Rated)
STEP 6Starting Inrush & Peak AsymmetryBS EN 60947-4-1I_LR = 7.2 × I_FLC; I_peak = √2 × I_LR × 1.457.2 × 14.3; √2 × 103.0 × 1.45103.0 A RMS / 211.2 A Peak
LAYER 6: WORKSHOP FAULT SIMULATOR & SAFE ISOLATION

AM2 Motor Breakdown & Safe Isolation Diagnostic Deck

Diagnose 10 real-world motor breakdowns conforming to C&G 2365 Unit 305 and NET AM2. Execute safe isolation per HSG85 with an approved two-pole voltage detector and prove dead across terminal studs before carrying out dead continuity and insulation tests.

FAULT INJECTION ENGINE

Breakdown Scenario

NORMAL OPERATION
Reported Symptom:

Motor operates conforms to BS EN 60034-1 specifications. No breakdown symptoms present.

Inspection Clue:

Verify terminal board links and phase resistances across U1-U2, V1-V2, and W1-W2.

Statutory Reference:

BS EN 60034-1 & BS 7671 Table 41.3

HSE GS38 INSTRUMENTATION

Safe Isolation & Multimeter Deck

HSG85 §46-52 Compliance
50V120V230V400V
DISCONNECTED
• 1. Initial Prove• 2. Test All Studs• 3. Final Re-ProveSYSTEM NOT PROVED DEAD

Apprentice Test Logbook

TimeInstrumentProbesReadingStatus
No measurements recorded. Select probes and apply test instrument.
LAYER 7: BENCH MENTOR PROCEDURES

Practical Workshop Procedures

Standard operating procedures for commissioning, connecting, and fault-finding industrial 3-phase induction motors.

JOB 1

Star vs Delta Linking

Inspect the motor rating plate. A 230/400V motor must connect in Star on UK 400V mains. A 400/690V motor connects in Delta. Delta links bridge U1-W2, V1-U2, W1-V2 vertically. Star links bridge W2-U2-V2 horizontally.

JOB 2

Safe Isolation per HSG85

Identify source of supply, isolate and lock off with safety padlock. Prove two-pole voltage detector on proving unit, test between all 6 phase-to-phase and phase-to-earth combinations, and re-prove on proving unit.

JOB 3

Stator Winding Verification

Remove linking bars. Measure resistance across U1-U2, V1-V2, and W1-W2 using a low-resistance ohmmeter. Readings must balance within 2%. Perform 500V DC insulation resistance to earth (minimum 1.0 megohm, typically over 100 megohms).

JOB 4

Direction of Rotation

Per BS EN 60034-8 §6.1, connecting L1-L2-L3 to U1-V1-W1 produces clockwise rotation viewed facing the Drive End shaft. To reverse shaft rotation to counter-clockwise, transpose any two incoming phase conductors (e.g. swap L1 and L2).

TECHNICAL ASSESSMENT

Apprentice CPD Verification Quiz (12 Questions)

Validate your understanding against British and International electrotechnical standards.

Question 1 of 12• Score 0 / 12
BS EN 60034-1 Section 4

Scenario: A dual-voltage nameplate reads 400V Delta / 690V Star, 7.5 kW, 50 Hz. The motor is to be connected directly to a standard UK 400V 3-phase supply.

How must the terminal box linking bridges be configured for continuous rated duty on this 400V supply?